Getting a permit can be complicated depending on your local municipality. Sometimes folks can find it overwhelming navigating the different government websites. We have put together an easy to use guide so you can easily get the answers you need about permitting in East Pikeland township.

east pikeland township park

What types of building projects require a building permit? A permit is required for new construction, additions, alterations, any project that requires structural changes, driveways, swimming pools, garages, sheds, signs, decks, as well as demolitions. Building permit applications are available at the township office. If you are still unsure whether or not a permit is required, please contact the township for more information.”

What does a permit cost in East Pikeland Township?

The East Pikeland website has a fee schedule available to help you determine the cost of getting a permit.

Permit Applications & Forms East Pikeland Township

Residential building permits take approximately three (3) weeks to process. Commercial building permits take up to six (6) weeks to process. Please plan accordingly. Please note: permit fees are doubled as a penalty if a project is started before applying and being issued necessary permits.

Print out the appropriate application form(s) for your project. Complete and return the completed form(s) for processing. You can hand-deliver the application to the township building or scan and email application to: [email protected].

Construction hours are 7:00 AM to 10:00 PM. No construction is permitted on Sundays or legal holidays.